A single-car 10×20 driveway at 5 inches thick takes 3.09 cubic yards — order 3.5 — and a two-car 20×20 at 5 inches takes 6.17 yards, order 7. Thickness, not length, is the number people get wrong.
Checked and reviewed by Zia ur Rehman, site owner · Last reviewed: November 2026 · The formula is shown on this page and the sources behind the numbers are listed at the foot of the page.
The short answer: 3.5 yards for one car, 7 for two
A single-car driveway 10 ft wide and 20 ft long, poured 5 inches thick, takes 3.09 cubic yards of concrete — order 3.5 yards with the waste allowance. A two-car driveway 20 × 20 ft at the same thickness takes 6.17 yards — order 7 yards. Both figures use the standard 10% waste allowance and round up to the nearest quarter yard, which is how ready-mix is sold.
Use the Concrete Calculator for the exact figure on your driveway — every number on this page matches it. The rest of this guide is the judgement around the number: how thick, how the joints are spaced, when bags beat a truck, and what it costs.
The formula
For a rectangular driveway, multiply length by width by thickness, with the thickness in inches:
The 324 comes from the unit conversion: 27 cubic feet in a yard times 12 inches in a foot. A 10 × 20 ft driveway at 5 inches is 10 × 20 × 5 ÷ 324 = 1,000 ÷ 324 = 3.09 cubic yards. Then add 10% for waste — uneven ground, spillage, form leaks — and round up to the next quarter yard: 3.09 × 1.10 = 3.40, which rounds up to an order of 3.5 yards. For the derivation and other materials, see our guide to calculating cubic yards, and for ordering in yards generally, our guide to how many yards of concrete you need.
Driveway sizes: yards to order
The table below gives the exact volume, the order with a 10% waste allowance, and the bag count if you mixed it yourself. The order column is rounded up to the nearest quarter yard:
| Driveway | Exact volume | Order (with 10% waste) | 80-lb bags |
|---|---|---|---|
| Single, 10 × 20 ft, 4 in | 2.47 yd³ | 2.75 yd³ | 112 bags |
| Single, 10 × 20 ft, 5 in | 3.09 yd³ | 3.5 yd³ | 139 bags |
| Single, 10 × 20 ft, 6 in | 3.70 yd³ | 4.25 yd³ | 167 bags |
| Single, 12 × 20 ft, 4 in | 2.96 yd³ | 3.5 yd³ | 134 bags |
| Single, 12 × 20 ft, 5 in | 3.70 yd³ | 4.25 yd³ | 167 bags |
| Single, 12 × 20 ft, 6 in | 4.44 yd³ | 5 yd³ | 200 bags |
| Two-car, 20 × 20 ft, 4 in | 4.94 yd³ | 5.5 yd³ | 223 bags |
| Two-car, 20 × 20 ft, 5 in | 6.17 yd³ | 7 yd³ | 278 bags |
| Two-car, 20 × 20 ft, 6 in | 7.41 yd³ | 8.25 yd³ | 334 bags |
| Two-car, 24 × 20 ft, 5 in | 7.41 yd³ | 8.25 yd³ | 334 bags |
| Two-car, 24 × 24 ft, 6 in | 10.67 yd³ | 11.75 yd³ | 480 bags |
The bag counts come from the yield of an 80-lb bag — 0.6 cubic feet, so 45 bags make one cubic yard. A 60-lb bag yields 0.45 cubic feet, so it takes 60 of them per yard; the two-car 20×20 at 5 inches would need 371 sixty-pound bags. For the full bag table, see our guide to bags of concrete per cubic yard.
How thick should a driveway be? 4, 5 or 6 inches
Thickness is the decision that moves the yardage most — and the one people most often underspecify. A driveway is not a patio: cars, and occasionally a delivery truck, park and turn on it every day.
| Thickness | Good for | Cost vs 4 in |
|---|---|---|
| 4 in | Light cars only, mild climate, firm ground | The baseline |
| 5 in | Most family driveways — the usual recommendation | +25% concrete vs 4 in |
| 6 in | Heavy vehicles, RVs, soft or clay soil, freeze-thaw winters | +50% concrete vs 4 in |
Going from 4 to 5 inches adds 25% to the concrete — the single 10×20 goes from 2.47 to 3.09 yards — and 4 to 6 inches adds 50%. That is the whole thickness decision in one line: an extra inch costs a quarter more concrete and buys a driveway that does not crack under a loaded pickup. Our guide to how thick a concrete slab should be covers the same rule for patios and garage floors.
Pour on a compacted gravel base, 4 inches deep, dampened before the pour — concrete poured straight onto soft soil cracks, whatever the thickness. Reinforcement is usually wire mesh or rebar on a grid; it does not add volume to the order, but it does add cost, so price it separately.
Worked examples: three real driveways
A single-car driveway, 12 × 20 ft at 5 inches. Volume is 12 × 20 × 5 ÷ 324 = 1,200 ÷ 324 = 3.70 cubic yards. Add 10% waste (3.70 × 1.10 = 4.07) and round up to the next quarter yard: order 4.25 yards. In bags that is 167 eighty-pound bags — over 6 tons of dry mix — which is why even a single-car driveway is a truck job, not a bag job. At the rough ready-mix prices below, the concrete alone is about $530–$765.
A two-car driveway, 20 × 20 ft at 6 inches. Volume is 20 × 20 × 6 ÷ 324 = 2,400 ÷ 324 = 7.41 cubic yards. With waste that is 8.15, rounded up to an order of 8.25 yards — one standard mixer truck, which carries about 10 yards. In bags it would be 334 eighty-pound bags, over 13 tons. At rough ready-mix prices the concrete is about $1,030–$1,485.
A long driveway, 12 × 40 ft at 5 inches. Volume is 12 × 40 × 5 ÷ 324 = 2,400 ÷ 324 = 7.41 cubic yards — the same volume as the 20×20 at 6 inches, because the area and thickness trade off exactly. Order 8.25 yards. Long driveways are poured in sections with a joint every 10–15 ft (see below), so the crew finishes one section while the next is still workable.
The apron. The apron — the strip where the driveway meets the street — is often poured thicker, 6 inches, because delivery trucks cut the corner over it. A 12 × 10 ft apron at 6 inches is 12 × 10 × 6 ÷ 324 = 720 ÷ 324 = 2.22 cubic yards — order 2.5 yards, or 100 eighty-pound bags. Check whether the apron is yours to pour: in many places the strip between the sidewalk and the street belongs to the city, and the thickness and mix are set by local code.
Control joints: where the cracks go
Concrete cracks — the joints decide where. Cut or form control joints at a spacing of 2–3 times the thickness in inches, measured in feet: a 4-inch driveway gets joints every 8–12 ft, a 5-inch driveway every 10–15 ft, and a 6-inch driveway every 12–18 ft. On a 20 ft driveway that means one joint across the middle at 10 ft, and on a 40 ft driveway three joints at roughly 10 ft intervals. Joints should also run along the centreline of a two-car driveway, and around any fixed point — a drain, a post, a corner — where a crack would otherwise start. Cut them within a day of the pour, while the concrete is still green, and to at least a quarter of the slab's depth.
Bags or a ready-mix truck?
The crossover is the same as for any slab, but driveways sit well past it. One cubic yard is 45 eighty-pound bags, and at roughly $7 a bag that is about $315 a yard against $125–$180 a yard for ready-mix. The single 10×20 driveway at 4 inches is 112 bags — about $784 of bagged mix, plus a mixer rental and a long day of mixing — against 2.75 yards of ready-mix at roughly $344–$495 before delivery. Even before the labour, the truck is cheaper on every driveway in the table above.
The one exception is the short-load fee: many suppliers charge extra for orders under about 3 yards, because the truck and driver cost the same whether they carry 1 yard or 10. A 2.75-yard order can carry a fee that narrows the gap — ask for it before ordering. Our guide to bagged concrete vs ready-mix works the crossover out job by job, and our guide to how much gravel a driveway needs covers the base underneath it.
Rough cost
Ready-mix concrete typically runs roughly $125–$180 per cubic yard, before delivery and any short-load fee — treat that as a rough range only, because prices vary by region and by mix. On that basis the single 10×20 at 5 inches (3.5 yards ordered) is roughly $440–$630 of concrete, the two-car 20×20 at 5 inches (7 yards) roughly $875–$1,260, and the two-car 24×24 at 6 inches (11.75 yards) roughly $1,470–$2,115. The concrete is only part of the job: the gravel base, forms, reinforcement, finishing and — on a long driveway — a second truck or a pump all add to the bill, so get a quote with the exact yardage in hand rather than a round number.
Common mistakes
- Pouring a driveway 4 inches thick for heavy vehicles. Four inches is a patio thickness. A family driveway wants 5 inches, and heavy vehicles or soft soil want 6 — the extra inch is 25% more concrete, not double.
- Ordering the exact volume. Uneven ground and spillage eat 5–10%. Add the waste allowance and round up to the next quarter yard — a cold joint halfway down a driveway is permanent.
- No control joints, or joints too far apart. A 20 ft driveway with no joint cracks where it pleases. Space joints 2–3 times the thickness in feet and cut them the same day.
- Forgetting the apron. The strip at the street is often thicker and sometimes city-controlled. Price it separately and check the local rules before pouring it.
- Bagging a driveway. Even the smallest driveway in the table is 112 bags. The truck is cheaper, faster, and gives a single consistent mix.
Frequently Asked Questions
How much concrete do I need for a single-car driveway?
A 10 × 20 ft driveway at 5 inches thick takes 3.09 cubic yards — order 3.5 yards with the 10% waste allowance. At 4 inches it is 2.47 yards (order 2.75), and at 6 inches it is 3.70 yards (order 4.25).
How much concrete for a two-car driveway?
A 20 × 20 ft driveway at 5 inches thick takes 6.17 cubic yards — order 7 yards. At 6 inches it is 7.41 yards (order 8.25). A larger 24 × 24 ft driveway at 6 inches takes 10.67 yards — order 11.75, more than one truckload.
How thick should a concrete driveway be?
5 inches is the usual recommendation for a family driveway; 6 inches for heavy vehicles, RVs, soft or clay soil, or freeze-thaw winters. Four inches is a patio thickness and is light for a driveway. Going from 4 to 5 inches adds 25% to the concrete, and 4 to 6 inches adds 50%.
How many bags of concrete for a driveway?
A single 10 × 20 ft driveway at 4 inches is 112 eighty-pound bags, and a two-car 20 × 20 ft at 5 inches is 278 bags. Driveways are truck jobs, not bag jobs — the same concrete as ready-mix costs roughly half as much per yard.
How far apart should control joints be on a driveway?
Space them 2–3 times the slab thickness in inches, measured in feet: 8–12 ft apart for a 4-inch driveway, 10–15 ft for 5 inches, and 12–18 ft for 6 inches. Cut them within a day of the pour, to at least a quarter of the slab's depth.
Sources and Method
The constants and rules of thumb on this page come from the published references below. Where a figure is a range, the calculator uses the mid-range value and the text says so.
- NRMCA CIP 31 — Ordering Ready-Mixed Concrete (ready-mix ordering and waste guidance).
- QUIKRETE Concrete Mix No. 1101 data sheet — published yield per bag (0.30 / 0.45 / 0.60 cu ft for 40 / 60 / 80 lb bags).
- Standard concrete density of about 150 lb per cubic foot.
- QUIKRETE Concrete Mix No. 1101 data sheet (PDF) — yield per bag: 0.30 cu ft (40 lb), 0.375 cu ft (50 lb), 0.45 cu ft (60 lb), 0.60 cu ft (80 lb); mixing water about 6 pt per 80 lb bag. Checked November 2026.