Rebar Calculator
Bars, total length and weight for a two-way rebar grid in a slab — plus how many 20 ft sticks to buy.
Checked and reviewed by Zia ur Rehman, site owner · Last reviewed: November 2026 · The formula is shown on this page and the sources behind the numbers are listed at the foot of the page.
Plain concrete is strong under compression but weak when it bends or stretches, which is exactly what a slab does as the ground settles, vehicles roll over it and temperatures change. A grid of steel reinforcing bar — rebar — tied across the slab in both directions is what gives the finished pour its strength and holds cracks tight. The trouble is estimating it: a grid looks simple, but the bar count, the total length and the weight all change quickly with slab size, spacing and bar size, and guessing usually means a second trip to the supplier or a pile of expensive steel left over.
Enter the slab length and width, choose a bar size and spacing, and this calculator works out how many bars run each way, the total length of steel in the grid, how many standard 20 ft sticks to buy and roughly what the grid will weigh. Work out the pour itself with the Concrete Calculator alongside it, so the steel and the concrete arrive in matching quantities for the same slab.
Rebar Calculator
| Bars in grid | 25 |
| Total length incl. laps | 475 ft |
| Total length before laps | 432 ft |
| Cut list | 11 bars × 19.5 ft + 14 bars × 15.5 ft |
| Total weight (approx) | 317 lb |
| Minimum lap splice (40 × bar diameter) | 20 in |
Grid counts assume bars stop 3 inches from the slab edge (concrete cover) — adjust the edge clearance to your spec. Weight uses standard published weights per foot for each bar size. The cut list shows the bars running each way at their full cut length — slab dimension minus twice the edge clearance — before any lap cuts are taken out of them.
How to Use This Calculator
- Measure the slab length and width in feet and inches, inside the forms. For an L-shaped or irregular slab, split it into rectangles and run the calculator once for each part.
- Choose the bar size and spacing from your plan or local practice: #4 bars at 18 inches each way is a common driveway grid, while #3 at 12–18 inches suits lighter patios and walkways.
- Set the edge clearance — 3 inches is typical so no bar end sits too close to the slab edge — and a lap allowance of about 10% to cover the overlaps where bars join.
- Buy the number of 20 ft sticks shown, and check the total weight before you decide how to get them home: a full grid is heavier than most people expect.
The Formula
The grid is counted one direction at a time. Bars running the length of the slab are spaced across its width, so take the width in inches, subtract twice the edge clearance, divide by the spacing and round down — then add 1, because a bar sits at both edges of the grid, not just in the gaps between them. That gives the count in one direction, and each of those bars is the slab length minus twice the edge clearance long. Repeat the same maths the other way — bars running the width, spaced along the length — and add the two lengths together for the total feet of steel in the grid. If you are also pricing the blocks or piers under a slab edge, the Concrete Block Calculator covers that count separately.
Stock bars are only so long, so wherever a run is longer than a single stick — or at a construction joint — two bars must overlap, or lap, so the steel acts as one continuous piece. A typical minimum lap is about 40 times the bar diameter, which quickly eats extra feet of steel across a whole grid, and that is what the lap allowance percentage covers. Finally, weight is simply total length multiplied by the published weight per foot for the bar size: #4 bar weighs 0.668 lb per foot, so every extra 100 feet of #4 adds about 67 lb to the load. The same slab volume that drives the steel count also drives the pour, so cross-check it with the Cubic Yards Calculator before ordering.
Worked Example
A 20 ft by 16 ft driveway slab with #4 bars at 18-inch spacing, 3 inches of edge clearance and a 10% lap allowance: across the 16 ft width, (192 − 6) ÷ 18 = 10.3, rounded down plus 1 gives 11 bars, each 19.5 ft long, for 214.5 ft. Along the 20 ft length, (240 − 6) ÷ 18 = 13, plus 1 gives 14 bars, each 15.5 ft long, for 217 ft. That is 25 bars in the grid and 431.5 ft of steel before laps. Adding 10% for laps brings it to about 475 ft, which is 475 ÷ 20 = 24 sticks of 20 ft rebar to buy, weighing about 317 lb in total.
A smaller 10 ft by 10 ft patio with #3 bars at 12-inch spacing, the same 3-inch edge and 10% lap: each direction needs (120 − 6) ÷ 12 = 9.5, rounded down plus 1, so 10 bars of 9.5 ft — 95 ft per direction and 190 ft in total. With the lap allowance that becomes 209 ft, or 11 sticks, and at 0.376 lb per foot for #3 bar the whole grid weighs only about 79 lb — an easy one-person load, unlike the driveway grid above. For a patio poured from bags rather than a truck, the Concrete Bag Calculator turns the same 10 by 10 dimensions into a bag count.
At the large end, a 24 ft by 24 ft garage slab with #4 bars at 18-inch spacing: each direction needs (288 − 6) ÷ 18 = 15.67, rounded down plus 1, so 16 bars of 23.5 ft — 32 bars and 752 ft of steel in the grid. With the 10% lap allowance that is 827 ft, or 42 sticks, weighing about 553 lb. A grid this size is a delivery, not a pickup, and the pour itself is 7.11 cubic yards at 4 inches — plan the steel and the truck together.
Rebar for Common Slabs (#4 bars, 3 in edge clearance, 10% lap allowance)
| Slab size | Spacing | Bars in grid | Total length incl. laps | 20 ft sticks | Weight |
|---|---|---|---|---|---|
| 10 × 10 ft | 18 in | 14 | 146 ft | 8 | 98 lb |
| 10 × 10 ft | 12 in | 20 | 209 ft | 11 | 140 lb |
| 12 × 12 ft | 18 in | 16 | 202 ft | 11 | 135 lb |
| 16 × 16 ft | 18 in | 22 | 375 ft | 19 | 251 lb |
| 20 × 16 ft | 18 in | 25 | 475 ft | 24 | 317 lb |
| 20 × 20 ft | 18 in | 28 | 601 ft | 31 | 401 lb |
| 20 × 20 ft | 12 in | 40 | 858 ft | 43 | 573 lb |
| 24 × 24 ft | 18 in | 32 | 827 ft | 42 | 553 lb |
Rebar Sizes — Diameter and Weight
Bar numbers are eighths of an inch: a #4 bar is 4/8 — one half — inch across. Weight per foot is what turns a length of steel into the load you have to carry:
| Bar size | Diameter | Weight |
|---|---|---|
| #3 | 0.375 in | 0.376 lb/ft |
| #4 | 0.500 in | 0.668 lb/ft |
| #5 | 0.625 in | 1.043 lb/ft |
| #6 | 0.750 in | 1.502 lb/ft |
| #7 | 0.875 in | 2.044 lb/ft |
| #8 | 1.000 in | 2.670 lb/ft |
Quick Answers
How much rebar do I need for a 12 × 12 slab?
With #4 bars at 18-inch spacing, a 12 × 12 ft slab takes 16 bars — 202 ft of steel once laps are included, 11 sticks, about 135 lb.
How much rebar for a 20 × 20 slab at 12-inch spacing?
40 bars of #4 — 858 ft with laps, 43 sticks, about 573 lb. Tightening the spacing from 18 to 12 inches adds roughly half as much steel again.
How many sticks of rebar for a 16 × 16 slab?
At 18-inch spacing with #4 bars: 22 bars, 375 ft with laps — 19 sticks, about 251 lb.
How much rebar for a 10 × 10 patio?
With light #3 bars at 12-inch spacing: 20 bars, 209 ft with laps — 11 sticks, and at #3's weight the whole grid is only about 79 lb.
How much does one 20 ft stick of rebar weigh?
A 20 ft stick of #4 weighs about 13.4 lb (0.668 lb/ft). The same stick in #3 is about 7.5 lb, and in #5 about 20.9 lb — the figure that decides whether a grid is a pickup load or a delivery.
Bar Size and Spacing by Slab Type
| Project | Bar size | Spacing (each way) | Notes |
|---|---|---|---|
| Walkway or patio, 4 in slab | #3 | 18 in | Light duty; welded wire mesh is the usual alternative |
| Driveway, 4–5 in slab | #4 | 12–18 in | Use 12 in where vehicles turn or the ground is soft — and the ACI 3× rule below caps a 4 in slab at 12 in |
| Garage floor | #4 | 12 in | Vehicle loads plus point loads from jacks and lifts |
| Slab on fill or poor soil | #4 | 12 in | The grid has to bridge soft spots; consider a thicker slab as well |
| Hot tub or RV pad, 6 in slab | #4–#5 | 12 in | Heavy point loads; at 6 in thick an 18 in grid is within the ACI cap |
Spacing and Cover: What ACI 318 Expects
ACI 318, the US concrete code, sets two guardrails this calculator's defaults respect. Maximum spacing: for slabs, reinforcement spacing should not exceed the lesser of 3 times the slab thickness or 18 inches — so a 4-inch slab caps at 12 inches by the 3× rule, and the popular 18-inch grid is really only code-consistent on slabs 6 inches and thicker, however common it is on 4-inch driveways. When in doubt, 12 inches is the defensible spacing for a 4-inch slab. Concrete cover — the concrete between the steel and the surface — is 3 inches for concrete cast against and permanently exposed to earth, 2 inches for concrete exposed to weather in larger members (1.5 inches for smaller bars and slabs in many cases), and 3/4 inch for interior slabs protected from weather. The edge clearance field in this calculator is the side cover; the grid also has to sit at the right height in the slab on chairs or dobies to get its bottom cover.
Cutting 20 ft Sticks into a Grid
The stick count is total length divided by 20, rounded up — but how you cut matters. In the worked example, the 25 bars are 11 bars of 19.5 ft and 14 bars of 15.5 ft. The 19.5 ft bars come one per stick with a 6-inch offcut; the 15.5 ft bars leave 4.5 ft offcuts, and two of those offcuts lapped together (with a proper 20-inch lap for #4) can serve as one more short bar where a run allows it. Plan the cutting list before the first cut: cut all the long bars first, keep offcuts sorted by length, and you will often save a stick over cutting as you go.
Common Rebar Mistakes
- Spacing a 4-inch slab at 18 inches. The ACI cap is the lesser of 3× the slab thickness or 18 inches — on a 4-inch slab that is 12 inches, whatever the neighbour's driveway used.
- Short laps. A lap under about 40× the bar diameter — 20 inches for #4 — does not transfer the load, and untied laps drift apart while the concrete is placed.
- No chairs. A grid that ends up lying on the gravel adds almost no strength, however much steel is in it. Support it at the height the plan calls for.
- No edge clearance. Bar ends at the slab face rust, stain and eventually spall the edge. The 3-inch clearance is part of the design, not lost coverage.
- Ordering the bare grid length. The lap allowance and cutting waste are real steel: order from the length including laps, plus a spare stick or two.
Sources and Method
The spacing and cover guardrails on this page are those of ACI 318, the Building Code Requirements for Structural Concrete, and the bar weights per foot and lap-splice practice follow the CRSI (Concrete Reinforcing Steel Institute) Manual of Standard Practice. Both were checked in November 2026 — an engineered design or a local code amendment still outranks the rules of thumb here.
Tips for an Accurate Estimate
- Buy one or two extra sticks beyond the calculated count. Cutting mistakes, a bent bar and the short offcuts that cannot be lapped into a run are normal, and a spare 20 ft stick is far cheaper than a second delivery.
- Keep the grid at the height the plan calls for — usually the middle or upper third of the slab — on chairs, dobies or small concrete blocks. Rebar left lying on the gravel during the pour adds almost no strength, no matter how much of it there is.
- Tie every intersection, or at least every second one, and lap bars by the full lap length before tying. A grid that shifts while concrete is placed ends up with wide and narrow bays that no longer match the design spacing.
- Plan transport from the weight figure, not the stick count. Twenty-four 20 ft sticks of #4 weigh over 300 lb and overhang any pickup bed, so delivery or a trailer is usually the sensible option — and store bars off the ground so they go in clean.
Frequently Asked Questions
How far apart should rebar be in a concrete slab?
For residential slabs, patios and driveways, 12 to 18 inches apart each way is the typical range: 18 inches suits lighter-duty slabs, while 12 inches is common for driveways and slabs on weaker ground. This calculator is a planning estimate — engineered work, commercial slabs and anything on a stamped plan should follow the spacing the plan specifies, and local code can set a maximum spacing for the slab thickness you are pouring.
What size rebar for a 4-inch slab / driveway?
#3 and #4 are the common residential choices. #3 (3/8 inch) is light, easy to cut and bend, and is often enough for patios and walkways. #4 (1/2 inch) is the usual driveway pick because it is noticeably stiffer and stronger for vehicle loads, and it is the default in this calculator. Stepping up to #5 or tightening the spacing adds strength, but for a standard 4-inch driveway slab a #4 grid at 12–18 inches is the combination most builders reach for.
How long should rebar laps be?
The rule of thumb is a lap of at least 40 times the bar diameter. For #4 bar that is 40 × 0.5 in = 20 inches, and 24–30 inches is common practice to give a comfortable margin and room to tie the bars together. Bigger bars need proportionally longer laps — #5 needs at least 25 inches by the same rule. Always follow local code or the lap length on the plan where one exists, and remember that laps are why this calculator adds a lap allowance on top of the bare grid length.
Rebar vs welded wire mesh — what is the difference?
Welded wire mesh is a factory-made grid of thin wires. It is cheap, fast to lay and does a good job of holding shrinkage cracks tight in light-duty slabs such as walkways and shed bases. Rebar is individual thick bars tied on site: it adds real bending strength, carries vehicle and point loads far better, and performs on poor or fill soils where a slab has to span soft spots. If the slab will carry cars, sit on questionable ground, or is part of an engineered design, rebar is the right choice; mesh is the light-duty alternative, not an equal substitute.
How much does rebar weigh?
Weight per foot rises fast with bar size: #3 weighs 0.376 lb/ft, #4 weighs 0.668 lb/ft, #5 weighs 1.043 lb/ft and #6 weighs 1.502 lb/ft, as shown in the table above. A single 20 ft stick of #4 is about 13.4 lb, and the 20 by 16 ft driveway grid in the worked example totals about 317 lb of steel once laps are included — plan transport, help for unloading and where the bundle will sit accordingly.
Sources and Method
The constants and rules of thumb on this page come from the published references below. Where a figure is a range, the calculator uses the mid-range value and the text says so.