How Much Concrete Do I Need for a Patio?
A patio is a flat slab with one decision that matters: how thick. The chart below gives yards, bags and the order quantity for the patio sizes people actually pour, at the standard 4 inches and at 6 inches for heavy use.
Checked and reviewed by Zia ur Rehman, site owner · Last reviewed: November 2026 · The formula is shown on this page and the sources behind the numbers are listed at the foot of the page.
The short answer: area × thickness, then add 10%
A patio is a rectangular slab, so the volume is cubic yards = length (ft) × width (ft) × thickness (in) ÷ 324 — the same formula the Concrete Calculator uses. Add the standard 10% waste allowance for an uneven sub-base and spillage, then round the order up to the next quarter yard, because ready-mix is sold in quarter-yard steps. For bags, divide the with-waste cubic feet by 0.60 — the yield of an 80 lb bag — and round up. Our guide to how much concrete you need covers the same formula for slabs in general; this guide is about the patio itself — its size, its thickness, and the shapes that are not rectangles.
How thick should a patio be?
4 inches is the standard for a patio that carries people, chairs and a grill — the same as a sidewalk — and it is what the chart below assumes. Go to 5 inches for a heavy outdoor kitchen, a large stone fireplace or a patio that will carry a loaded wheelbarrow of firewood every week. Pour 6 inches where the patio carries real weight: a hot tub, a vehicle, or a section that doubles as a driveway crossing (our sidewalk guide pours its driveway crossings at 6 inches for the same reason). Under the slab, put 4 inches of compacted gravel base — our guide to how thick gravel should be covers the base depths — and if the patio is thicker at the edges, count the thickened edge separately: a 4-inch slab with a 12-inch-deep edge beam around the outside takes noticeably more concrete than the flat-slab figure, and the calculator's slab mode does not include it. For the slab thickness itself, see our guide to how thick a concrete slab should be.
Concrete for common patio sizes (4 inches thick)
The table is for a 4-inch-thick patio with the 10% waste allowance included. The "order" column rounds up to the next quarter yard, and the bag column counts 80 lb bags from the with-waste volume. For a 6-inch patio, multiply the yards and the bags by 1.5 — the worked 16×20 example below shows it.
| Patio size | Net cubic yards | Order (with 10% waste) | 80 lb bags |
|---|---|---|---|
| 8 × 8 ft | 0.79 | 1.00 yd³ | 40 |
| 10 × 10 ft | 1.23 | 1.50 yd³ | 62 |
| 12 × 12 ft | 1.78 | 2.00 yd³ | 88 |
| 12 × 16 ft | 2.37 | 2.75 yd³ | 118 |
| 10 × 20 ft | 2.47 | 2.75 yd³ | 123 |
| 14 × 18 ft | 3.11 | 3.50 yd³ | 154 |
| 16 × 20 ft | 3.95 | 4.50 yd³ | 196 |
| 20 × 20 ft | 4.94 | 5.50 yd³ | 245 |
Two things the table makes plain. First, a patio crosses the bag-to-truck line fast: a 10×10 is a bag job if you are determined, but a 16×20 at 196 bags is a truck job by any measure. Second, the waste allowance is not padding — a patio poured on a gravel base that is an inch low in places drinks the extra 10% before the pour is half done.
Worked examples
A 12 × 16 ft patio at 4 inches — the common backyard size. The volume is 12 × 16 × 4 ÷ 324 = 2.37 cubic yards. With 10% waste that is 2.61 yards, so order 2.75 cubic yards. In bags that is 2.61 × 27 = 70.4 cu ft, and 70.4 ÷ 0.60 = 117.3, so 118 bags of 80 lb mix. At the site's rough ready-mix range of $125–$180 per cubic yard, the truck costs 2.75 × $125–$180 = $344–$495, against 118 × $7 = $826 in bags — the truck wins by a wide margin, and 118 bags is a full day of mixing by hand.
A small 10 × 10 ft patio at 4 inches. The volume is 10 × 10 × 4 ÷ 324 = 1.23 cubic yards. With 10% waste that is 1.36 yards, so order 1.50 cubic yards, or 62 bags (36.7 cu ft ÷ 0.60 = 61.1, rounded up). The truck costs 1.50 × $125–$180 = $188–$270 against 62 × $7 = $434 in bags — but watch the short-load fee: most suppliers charge extra under about 3 yards, so a 1.5-yard order can carry a $50–$150 fee on top. Even with the fee, the truck is usually cheaper, and it is incomparably less work. Our guide to bagged concrete vs ready-mix works out the crossover in detail.
A round patio, 12 ft across, at 4 inches. The area is π × 6² = 113.10 sq ft, so the volume is 113.10 × 4 ÷ 324 = 1.40 cubic yards. With 10% waste that is 1.54 yards, so order 1.75 cubic yards, or 70 bags (41.5 cu ft ÷ 0.60 = 69.1, rounded up). Measure the diameter through the centre of the circle, not across a chord, and form the circle with flexible form boards — a round patio is measured the same way as the round bed in our raised-bed topsoil guide.
An L-shaped patio: 20 × 16 ft overall with an 8 × 6 ft corner missing, at 4 inches. Split it into rectangles and count the corner once: the area is 20 × 16 − 8 × 6 = 320 − 48 = 272 sq ft. The volume is 272 × 4 ÷ 324 = 3.36 cubic yards. With 10% waste that is 3.69 yards, so order 3.75 cubic yards, or 167 bags (99.7 cu ft ÷ 0.60 = 166.2, rounded up). Our guide to measuring an L-shaped room uses the same split-into-rectangles method — the corner belongs to one leg or the other, never both.
A heavy-use 16 × 20 ft patio at 6 inches, for a hot tub. The volume is 16 × 20 × 6 ÷ 324 = 5.93 cubic yards. With 10% waste that is 6.52 yards, so order 6.75 cubic yards, or 294 bags (176.0 cu ft ÷ 0.60 = 293.4, rounded up). At 6 inches the same footprint takes half as much again as at 4 inches — which is why thickness is decided before the order is placed, not after the truck arrives. A hot tub also wants the slab reinforced and the ground properly compacted; the concrete quantity is the easy part of that job.
Control joints — the part that stops the cracking
Concrete shrinks as it cures, and a patio without joints cracks wherever it pleases. Control joints give it a planned place to crack: a groove cut or tooled across the slab at regular intervals, about a quarter of the slab's depth (1 inch deep on a 4-inch patio). Space them no more than 2–3 times the thickness in inches, in feet — 8–12 ft apart for a 4-inch slab, the same rule our driveway guide uses. On a patio, the practical spacing is usually tighter: a 12×16 patio with joints every 8 ft reads as four tidy panels, while a 16 ft run with no joint reads as a crack waiting to happen. Tool the joints while the concrete is still workable, or saw-cut them the same day — a joint cut a week later is a decoration, not a control joint.
Bags or a truck?
The crossover is about 1 cubic yard — 45 bags of 80 lb mix, roughly $315 in bags against $125–$180 a yard from a truck. Below a yard, bags can be cheaper once delivery is counted; above it, the truck wins on price and overwhelmingly on labour. The catch for patios is the short-load fee: most suppliers charge extra for orders under about 3 cubic yards. A 1.5-yard patio might carry a $50–$150 fee on top of the per-yard price — ask the supplier before ordering. Even with the fee, the 10×10 patio above costs $188–$270 plus the fee against $434 in bags, and the concrete arrives mixed, in one pour, instead of 62 bags into a wheelbarrow.
Common mistakes
- Ordering the net volume. The 12×16 patio needs 2.37 yards net and 2.61 with waste, and the truck is ordered at 2.75. Ordering exactly 2.37 runs out a few feet from the end.
- Measuring the outside of the forms. Measure the inside of the forms — the concrete goes inside them. An inch of formwork on each side overstates a 12 ft patio by over 4%.
- Pouring 4 inches under a hot tub. A hot tub is thousands of pounds on a small footprint. Pour its pad at 6 inches, reinforced, or pour a separate thicker pad under it.
- Forgetting the thickened edge. A patio with a deep edge beam takes more concrete than the flat-slab figure. Count the edge separately.
- Spacing the joints too far apart. Joints belong no more than 8–12 ft apart on a 4-inch patio. A 20 ft run with one joint will crack between them.
- Skipping the gravel base. Four inches of compacted gravel under the slab stops the patio settling and cracking. Concrete on soft soil is a temporary patio.
Frequently Asked Questions
How much concrete do I need for a 12x16 patio?
A 12×16 ft patio at 4 inches thick takes 2.37 cubic yards net — order 2.75 cubic yards with the 10% waste allowance, or 118 bags of 80 lb mix. At 6 inches thick the same patio takes 3.56 yards net, so order 4.00 yards or 176 bags.
How thick should a concrete patio be?
4 inches for a patio that carries people, chairs and a grill, on a 4-inch compacted gravel base. Pour 5 inches for a heavy outdoor kitchen and 6 inches where the patio carries a hot tub or a vehicle.
How many bags of concrete for a patio?
Divide the with-waste cubic feet by 0.60 (the yield of an 80 lb bag). A 10×10 ft patio at 4 inches takes 62 bags; a 12×16 takes 118; a 16×20 takes 196 — at that size, order ready-mix instead.
Is it cheaper to use bags or ready-mix for a patio?
Ready-mix is cheaper above about 1 cubic yard: a 12×16 ft patio costs roughly $344–$495 from a truck (2.75 yards at $125–$180 per yard) against $826 in bags — plus a possible short-load fee under about 3 yards, so ask the supplier. Below a yard, bags can win once delivery is counted.
How far apart should control joints be on a patio?
No more than 2–3 times the thickness in inches, in feet — 8–12 ft apart for a 4-inch patio. In practice, joints every 8 ft give tidy panels on a 12×16 patio and control cracking better than the outer limit.
Sources and Method
The constants and rules of thumb on this page come from the published references below. Where a figure is a range, the calculator uses the mid-range value and the text says so.
- NRMCA CIP 31 — Ordering Ready-Mixed Concrete (ready-mix ordering and waste guidance).
- QUIKRETE Concrete Mix No. 1101 data sheet — published yield per bag (0.30 / 0.45 / 0.60 cu ft for 40 / 60 / 80 lb bags).
- Standard concrete density of about 150 lb per cubic foot.
- QUIKRETE Concrete Mix No. 1101 data sheet (PDF) — yield per bag: 0.30 cu ft (40 lb), 0.375 cu ft (50 lb), 0.45 cu ft (60 lb), 0.60 cu ft (80 lb); mixing water about 6 pt per 80 lb bag. Checked November 2026.