How Much Concrete Do I Need?
Multiply length × width × thickness, divide by 27 — then add 10% for waste. A 10×10 ft slab at 4 inches thick needs 1.23 cubic yards (order 1.5), or 56 bags of 80-lb premix.
Checked and reviewed by Zia ur Rehman, site owner · Last reviewed: November 2026 · The formula is shown on this page and the sources behind the numbers are listed at the foot of the page.
The formula
Cubic yards = (length in ft × width in ft × thickness in ft) ÷ 27. Thickness in inches ÷ 12 = thickness in feet. So a 4-inch slab is 0.33 ft thick, a 6-inch slab is 0.5 ft thick. Always round up — running short mid-pour is far worse than having a little extra, and most suppliers sell in quarter-yard steps anyway.
Use the Concrete Calculator for exact numbers on any size — the table below covers the common ones.
Concrete needed by slab size (4 inches thick)
| Slab size | Area | Cubic feet | Cubic yards | Cu yd with 10% waste | 80 lb bags | 60 lb bags |
|---|---|---|---|---|---|---|
| 4 × 4 ft | 16 sq ft | 5.33 | 0.20 | 0.22 | 9 | 12 |
| 6 × 6 ft | 36 sq ft | 12.00 | 0.44 | 0.49 | 20 | 27 |
| 8 × 8 ft | 64 sq ft | 21.33 | 0.79 | 0.87 | 36 | 48 |
| 8 × 10 ft | 80 sq ft | 26.67 | 0.99 | 1.09 | 45 | 60 |
| 10 × 10 ft | 100 sq ft | 33.33 | 1.23 | 1.36 | 56 | 75 |
| 10 × 12 ft | 120 sq ft | 40.00 | 1.48 | 1.63 | 67 | 89 |
| 12 × 12 ft | 144 sq ft | 48.00 | 1.78 | 1.96 | 80 | 107 |
| 12 × 16 ft | 192 sq ft | 64.00 | 2.37 | 2.61 | 107 | 143 |
| 16 × 16 ft | 256 sq ft | 85.33 | 3.16 | 3.48 | 143 | 190 |
| 20 × 20 ft | 400 sq ft | 133.33 | 4.94 | 5.43 | 223 | 297 |
| 20 × 30 ft | 600 sq ft | 200.00 | 7.41 | 8.15 | 334 | 445 |
| 24 × 24 ft | 576 sq ft | 192.00 | 7.11 | 7.82 | 320 | 427 |
This is the same slab-size table the concrete calculator page uses — same rows, same numbers, one source. Bag counts are net: exact division rounded up (e.g. 33.3 ÷ 0.6 = 55.6 → 56 bags) with no waste added. The waste column adds 10% to the yardage; round that figure up to the next quarter yard to get the order quantity, as the rounding section below explains. For a 6-inch slab, multiply the yards and the bags by 1.5.
How far does a cubic yard go? Coverage by thickness
The same yard covers very different areas depending on thickness — the second table shared with the calculator page:
| Thickness | Sq ft one cubic yard covers | Sq ft one 80 lb bag covers |
|---|---|---|
| 3 in | 108 | 2.4 |
| 4 in | 81 | 1.8 |
| 5 in | 64.8 | 1.44 |
| 6 in | 54 | 1.2 |
| 8 in | 40.5 | 0.9 |
One cubic yard at 4 inches covers 81 sq ft, which is why a 10×10 slab (100 sq ft) needs more than a yard. For any size not in the tables, run it through the calculator linked above — it returns the same figures, including the order rounding.
How thick should the slab be?
- 4 inches — patios, walkways, shed floors, light foot traffic. The standard for most home slabs.
- 5–6 inches — driveways, garage floors, anything a car or truck will park on. A 10×10 slab at 6 inches needs 1.85 cubic yards (84 × 80-lb bags) instead of 1.23.
- 8 inches+ — heavy loads, hot tubs, RV pads. Get an engineer or a contractor to spec these; thickness alone is not the whole story (rebar and base matter).
Footings, round slabs and post holes
Not every pour is a rectangle. The same volume formula adapts:
- Strip footing: length of run × width × depth. A 24 ft footing run, 16 inches wide and 8 inches deep, is 24 × 1.33 × 0.67 = 21.3 cu ft — 0.79 cubic yards. The Concrete Calculator's footing shape does this directly.
- Round slab: π × radius² × thickness. A 12 ft diameter patio at 4 inches is 3.14159 × 36 × 0.33 = 37.7 cu ft — 1.40 cubic yards.
- Post holes: a cylinder, π × radius² × depth, times the number of holes. Ten holes at 12 inches wide and 3 ft deep are 10 × 2.36 = 23.6 cu ft — 40 × 80-lb bags. Use the calculator's round column shape with the quantity set to the number of holes.
Thickness quick reference
| Use | Thickness | Notes |
|---|---|---|
| Patio, walkway, shed floor | 4 in | The residential standard. |
| Driveway (cars) | 5–6 in | 4 in is a minimum; 5–6 in carries vehicles better. |
| Garage floor | 5–6 in | Over a compacted gravel base. |
| RV pad, hot tub base | 6–8 in | Heavy point loads — reinforcement matters as much as thickness. |
| Strip footing | 8 in or more | Depth and width are set by load and local code; the bottom must sit below the frost line. |
Worked example: a 20×40 ft driveway
A single-car driveway 20 ft wide and 40 ft long, poured 5 inches thick for vehicle loads: volume = 20 × 40 × (5 ÷ 12) = 333.3 cu ft = 12.35 cubic yards. Add the standard 10% waste and the order is 13.5 yards — one full truck plus a second small load, or a single 10-yard truck and a follow-up, which is worth discussing with the supplier. In bags the same driveway would be 556 × 80-lb bags — over 22 tons of dry mix — which is why nobody bags a driveway. At the planning prices below, the concrete alone runs roughly $1,550–$2,220 before delivery, base gravel and reinforcement.
Requirement vs order quantity: how ready-mix rounding works
The yardage the formula gives you is the requirement — the volume of the hole you are filling. The order quantity is what the plant will actually sell and deliver, and the two are never the same number, for three reasons. First, the waste allowance: uneven ground, spillage and form leaks eat 5–10%, so the requirement is increased by 10% before anything else happens. Second, suppliers batch and deliver in quarter-yard steps — you can order 1.5 or 1.75 yards, not 1.63 — so the waste-included figure is rounded up to the next quarter yard. Third, most plants have a minimum order of about 1 cubic yard: below that there is nothing to round to, and the job belongs to bags. Worked through for the standard 10×10 slab: requirement 1.23 yards, plus 10% waste is 1.36 yards, rounded up to the next quarter yard gives an order of 1.5 yards.
One more wrinkle: orders under roughly 3–4 yards commonly carry a short-load fee, because the truck and driver cost the plant the same whether they carry 1 yard or 10. The fee belongs in the order-quantity decision — on a small job it can make bags cheaper than the truck even when the yardage says otherwise, which is the comparison priced out below.
Ordering checklist
- Quantity: calculated yards + 10% waste, rounded up to the next quarter yard.
- Strength: 3,000 PSI for patios and walkways; 3,500–4,000 PSI for driveways.
- Air-entrained mix if the slab faces freeze-thaw weather.
- Ask about the short-load fee if you are ordering under 3–4 yards.
- Forms built, gravel base compacted and dampened, tools and help on site before the truck arrives — you get about 90 minutes of working time.
- Agree where the truck washes out, and how it reaches the pour (chute reach is roughly 10–12 ft).
Bags or a ready-mix truck?
One cubic yard takes 45 bags of 80-lb mix (or 60 bags of 60-lb). That is the rule of thumb that decides it:
- Under ~0.5 cubic yards (a few post holes, a small pad): bags are cheaper and simpler. A 12-inch-diameter post hole 3 ft deep takes about 2.36 cu ft — just 4 × 80-lb bags.
- Over ~0.5 cubic yards: a ready-mix delivery is usually cheaper per yard and far less work. Fifty-six 80-lb bags is over 2 tons of mixing by hand.
- Watch the short-load fee: most ready-mix suppliers charge extra for orders under 3–4 cubic yards, so a 1.5-yard order can cost nearly as much as a 3-yard one. Ask for the fee before you order.
See also: How Many Bags of Concrete Are in a Cubic Yard?
What does it cost? (2026, US, rough ranges)
Prices vary a lot by region — treat these as planning numbers and get a local quote before ordering:
- Ready-mix: roughly $125–$180 per cubic yard, plus delivery and any short-load fee. A 10×10 slab at 4 inches (1.5 yd ordered) is roughly $190–$270 + fees.
- Bagged premix: an 80-lb bag is roughly $5–$7 at a home center. The same 10×10 slab in bags is 56 bags, roughly $280–$390 — more expensive than ready-mix, before you count a mixer rental.
- Extras people forget: gravel base (4 inches of compacted gravel under most slabs), rebar or wire mesh, forms, a mixer rental (~$50–$75/day), and finishing tools.
Common mistakes
- Forgetting waste. Uneven ground, spillage and form leaks eat 5–10%. Order the extra 10% — leftover concrete can become a stepping stone, a short pour cannot be topped up cleanly.
- Mixing up inches and feet. Thickness in inches must be divided by 12 before multiplying. This one error makes the answer 12× too big.
- Ordering exactly the calculated amount. Suppliers round down, trucks leave a little behind, and a slab poured in two batches has a visible cold joint. Round up to the next quarter yard.
- No base. Concrete poured straight onto soft soil cracks. Compact 4 inches of gravel first and dampen it before the pour.
Quick answers for other slab sizes
The chart above covers the most-asked sizes. These four come up almost as often — every figure is the same maths the concrete calculator runs:
How much concrete do I need for an 8×10 slab?
At 4 inches thick, an 8 × 10 ft slab is 26.67 cu ft = 0.99 cubic yards — order 1.25 yards with waste and rounding — or 45 bags of 80-lb mix.
How much concrete do I need for a 16×16 slab?
At 4 inches thick: 85.33 cu ft = 3.16 cubic yards — order 3.5 yards — or 143 bags of 80-lb mix.
How much concrete do I need for a 20×30 slab?
At 4 inches thick: 200 cu ft = 7.41 cubic yards — order 8.25 yards, one full truck — or 334 bags, which is why this size is never bagged.
How much concrete do I need for a 6×6 slab?
At 4 inches thick: 12 cu ft = 0.44 cubic yards. That is below most plants' 1-yard minimum order, so this is a bag job: 20 bags of 80-lb mix.
Frequently Asked Questions
How many 80-lb bags of concrete in a yard?
45 bags. One yard is 27 cu ft and one 80-lb bag makes 0.6 cu ft (27 ÷ 0.6 = 45).
How much concrete for a 10×10 slab?
At 4 inches thick: 1.23 cubic yards — order 1.5. In bags: 56 × 80-lb or 75 × 60-lb. At 6 inches thick: 1.85 cubic yards — order 2.
How much concrete for a 20×20 slab?
At 4 inches thick: 4.94 cubic yards — order 5.5. In bags: 223 × 80-lb. This size is a ready-mix job, not a bag job.
How do I calculate concrete for post holes?
Volume of a cylinder: π × radius² × depth. A 12-inch-wide hole 3 ft deep is about 2.36 cu ft — 4 × 80-lb bags. Try the Concrete Calculator and enter the hole as a round shape, or use the Cubic Yards Calculator for the volume first.
Can I pour concrete in cold weather?
Yes, with precautions: keep the mix above about 40°F (4°C) while it cures, cover it with insulating blankets, and never pour onto frozen ground. Below freezing, wait for a warmer day.
Sources and Method
The constants and rules of thumb on this page come from the published references below. Where a figure is a range, the calculator uses the mid-range value and the text says so.
- NRMCA CIP 31 — Ordering Ready-Mixed Concrete (ready-mix ordering and waste guidance).
- QUIKRETE Concrete Mix No. 1101 data sheet — published yield per bag (0.30 / 0.45 / 0.60 cu ft for 40 / 60 / 80 lb bags).
- Standard concrete density of about 150 lb per cubic foot.