Concrete for Common Slab Sizes: 10×20, 12×12, 20×20, 24×24
A 12×12 ft slab at 4 inches takes 1.78 cubic yards (order 2) or 80 bags; a 24×24 ft slab at 6 inches takes 10.67 yards (order 11.75) — 480 bags, so that one is a truck job.
Checked and reviewed by Zia ur Rehman, site owner · Last reviewed: November 2026 · The formula is shown on this page and the sources behind the numbers are listed at the foot of the page.
The short answer: one chart, four sizes, three thicknesses
Four slab sizes cover most home projects — a 12×12 patio, a 10×20 driveway strip, a 20×20 garage floor and a 24×24 garage or workshop. The chart below gives each one at 4, 5 and 6 inches thick: the exact volume, the order quantity with a 10% waste allowance, the bag count, and the ready-mix cost. Going from 4 to 6 inches adds 50% more concrete, so the thickness column matters as much as the size.
Use the Concrete Calculator for exact numbers on any size — the chart below covers the common ones.
Concrete by slab size and thickness
| Slab size | Thickness | Cubic feet | Cubic yards | Order (+10% waste) | 80-lb bags | Ready-mix cost (rough) |
|---|---|---|---|---|---|---|
| 10×20 ft | 4 in | 66.7 | 2.47 | 2.75 yd | 112 | $344–$495 |
| 10×20 ft | 5 in | 83.3 | 3.09 | 3.5 yd | 139 | $438–$630 |
| 10×20 ft | 6 in | 100.0 | 3.70 | 4.25 yd | 167 | $531–$765 |
| 12×12 ft | 4 in | 48.0 | 1.78 | 2 yd | 80 | $250–$360 |
| 12×12 ft | 5 in | 60.0 | 2.22 | 2.5 yd | 100 | $312–$450 |
| 12×12 ft | 6 in | 72.0 | 2.67 | 3 yd | 120 | $375–$540 |
| 20×20 ft | 4 in | 133.3 | 4.94 | 5.5 yd | 223 | $688–$990 |
| 20×20 ft | 5 in | 166.7 | 6.17 | 7 yd | 278 | $875–$1,260 |
| 20×20 ft | 6 in | 200.0 | 7.41 | 8.25 yd | 334 | $1,031–$1,485 |
| 24×24 ft | 4 in | 192.0 | 7.11 | 8 yd | 320 | $1,000–$1,440 |
| 24×24 ft | 5 in | 240.0 | 8.89 | 10 yd | 400 | $1,250–$1,800 |
| 24×24 ft | 6 in | 288.0 | 10.67 | 11.75 yd | 480 | $1,469–$2,115 |
Costs use the ready-mix range of $125–$180 per cubic yard from our concrete guide, applied to the ordered volume — before delivery and any short-load fee. Bag counts are exact division rounded up (e.g. 66.7 ÷ 0.6 = 111.1 → 112 bags) and do not include waste — add 10% when buying bags. The "order" column already includes the 10% waste allowance, rounded up to the next quarter yard.
All the common sizes at 4 inches
The chart above follows four sizes through three thicknesses. For the full run of common sizes at the standard 4 inches, this is the same slab-size table the concrete calculator page uses — identical rows and numbers:
| Slab size | Area | Cubic feet | Cubic yards | Cu yd with 10% waste | 80 lb bags | 60 lb bags |
|---|---|---|---|---|---|---|
| 4 × 4 ft | 16 sq ft | 5.33 | 0.20 | 0.22 | 9 | 12 |
| 6 × 6 ft | 36 sq ft | 12.00 | 0.44 | 0.49 | 20 | 27 |
| 8 × 8 ft | 64 sq ft | 21.33 | 0.79 | 0.87 | 36 | 48 |
| 8 × 10 ft | 80 sq ft | 26.67 | 0.99 | 1.09 | 45 | 60 |
| 10 × 10 ft | 100 sq ft | 33.33 | 1.23 | 1.36 | 56 | 75 |
| 10 × 12 ft | 120 sq ft | 40.00 | 1.48 | 1.63 | 67 | 89 |
| 12 × 12 ft | 144 sq ft | 48.00 | 1.78 | 1.96 | 80 | 107 |
| 12 × 16 ft | 192 sq ft | 64.00 | 2.37 | 2.61 | 107 | 143 |
| 16 × 16 ft | 256 sq ft | 85.33 | 3.16 | 3.48 | 143 | 190 |
| 20 × 20 ft | 400 sq ft | 133.33 | 4.94 | 5.43 | 223 | 297 |
| 20 × 30 ft | 600 sq ft | 200.00 | 7.41 | 8.15 | 334 | 445 |
| 24 × 24 ft | 576 sq ft | 192.00 | 7.11 | 7.82 | 320 | 427 |
And the coverage table that pairs with it — how far a yard, or one 80-lb bag, goes at each thickness:
| Thickness | Sq ft one cubic yard covers | Sq ft one 80 lb bag covers |
|---|---|---|
| 3 in | 108 | 2.4 |
| 4 in | 81 | 1.8 |
| 5 in | 64.8 | 1.44 |
| 6 in | 54 | 1.2 |
| 8 in | 40.5 | 0.9 |
How to read the chart
Three numbers decide every row. Cubic yards is the exact volume: length × width × thickness in feet, divided by 27. Order is that volume plus 10% for waste — uneven ground, spillage and form leaks — rounded up to the next quarter yard, because suppliers sell in quarter-yard steps and a slab poured in two batches has a visible cold joint. Bags is the exact count of 80-lb bags (each yields 0.60 cubic feet), rounded up; 60-lb bags would be a third more again.
A 10×10 ft slab at 4 inches — the most quoted size of all — takes 1.23 cubic yards (order 1.5) or 56 bags, and is covered in detail in How Much Concrete Do I Need?.
What is each size used for?
| Slab size | Area | Typical use |
|---|---|---|
| 12×12 ft | 144 sq ft | Small patio, shed floor, hot-tub pad (at 6 in). |
| 10×20 ft | 200 sq ft | Single-car driveway strip, large patio, walkway plus pad. |
| 20×20 ft | 400 sq ft | Two-car garage floor, large patio, one driveway section. |
| 24×24 ft | 576 sq ft | Two-car garage, workshop floor, RV pad (at 6 in). |
The size follows the job, not the other way round: a patio is sized by the furniture it holds, a garage by the cars plus walking room, and a driveway by the vehicles that park on it. Measure the finished slab you want, not the hole you dug — the forms sit outside the slab edge, so the excavation is always a few inches wider than the slab itself.
Which thickness for which slab?
- 4 inches — patios, walkways, shed floors, light foot traffic. The standard for most home slabs, and the cheapest row in the chart.
- 5 inches — driveways and garage floors that carry cars every day. The middle row is the sensible default for anything a vehicle parks on.
- 6 inches — driveways with heavy vehicles, RV pads, hot-tub bases. Going from 4 to 6 inches adds exactly 50% more concrete: a 20×20 slab goes from 4.94 to 7.41 cubic yards, and the cost follows it.
Thickness is measured after the base is compacted, and a gravel base of 2–4 inches under the slab is normal practice — the base does not count as slab thickness. See How Thick Should a Concrete Slab Be? for the full thickness-by-use guide.
Worked example: a 20×20 ft garage floor at 5 inches
The volume is 20 × 20 × (5 ÷ 12) = 166.7 cubic feet, or 6.17 cubic yards. Add 10% for waste and the order is 7 yards. At $125–$180 per yard the concrete alone is roughly $875–$1,260, before delivery, the gravel base and reinforcement. In bags the same floor would be 278 × 80-lb bags — 22,240 lb, over 11 tons of dry mix to lift twice and mix in batches. That is why a garage floor is a ready-mix job, and why the truck's short-load fee (orders under 3–4 yards) does not bite here: a 7-yard order is well past it.
Bags or a ready-mix truck?
Count the lifting, not just the money. One cubic yard of bags is 3,600 lb; the chart's bag counts translate directly into weight:
- 12×12 ft at 4 inches — 80 bags, 6,400 lb. The biggest realistic bag job: two people, a rented drum mixer and a day. Possible, and the only size in this chart where bags are a genuine option.
- 10×20 ft at 4 inches — 112 bags, 8,960 lb. Price the truck first; bags only make sense if the truck cannot reach the pour.
- 20×20 ft at 4 inches — 223 bags, 17,840 lb. A truck job. Mixing 223 bags by hand means the first batch has started to set before the last is placed — a cold joint across the middle of the slab.
- 24×24 ft at 6 inches — 480 bags, 38,400 lb (19.2 tons). Not a bag job at any price. One truck, one continuous pour, no seams.
The full bags-vs-truck maths — including the short-load fee that decides the small end of the chart — is in Bagged Concrete vs Ready-Mix: Which Should You Use?.
Common mistakes
- Ordering the exact calculated amount. Uneven ground, spillage and form leaks eat 5–10%. Order the extra — leftover concrete can become a stepping stone, a short pour cannot be topped up cleanly.
- Counting the gravel base as concrete. The 4 inches of compacted gravel under a slab is base, not concrete — measure only the concrete depth, or you will order a yard you do not need.
- Mixing up inches and feet. Thickness in inches must be divided by 12 before multiplying. This one error makes the answer 12× too big.
- Picking thickness by size instead of by load. A 24×24 patio is still a 4-inch slab; a 12×12 RV pad is a 6-inch slab. The load decides the thickness, not the area.
- Bagging a big slab. Past about 80 bags the labour and the cold joints cost more than the truck's fee — and a slab poured in batches shows the seam forever.
Quick answers for other slab sizes
How much concrete for a 14×14 slab?
At 4 inches thick: 65.33 cu ft = 2.42 cubic yards — order 2.75 yards — or 109 bags of 80-lb mix.
How much concrete for an 18×18 slab?
At 4 inches thick: 108 cu ft = 4.00 cubic yards — order 4.5 yards — or 180 bags.
How much concrete for a 10×16 slab?
At 4 inches thick: 53.33 cu ft = 1.98 cubic yards — order 2.25 yards — or 89 bags.
How much concrete for a 40×20 slab?
At 4 inches thick: 266.67 cu ft = 9.88 cubic yards — order 11 yards, so two loads — or 445 bags.
Frequently Asked Questions
How much concrete for a 12×12 slab?
At 4 inches thick: 1.78 cubic yards — order 2 yards, or 80 bags of 80-lb mix. At 6 inches: 2.67 cubic yards — order 3 yards, or 120 bags. At $125–$180 per yard, the ready-mix concrete is roughly $250–$360 at 4 inches.
How much concrete for a 20×20 slab?
At 4 inches thick: 4.94 cubic yards — order 5.5 yards, or 223 bags of 80-lb mix. At 6 inches: 7.41 cubic yards — order 8.25 yards, or 334 bags. This size is a ready-mix job, not a bag job.
How much concrete for a 24×24 slab?
At 4 inches thick: 7.11 cubic yards — order 8 yards, or 320 bags. At 6 inches: 10.67 cubic yards — order 11.75 yards, or 480 bags (38,400 lb). A 24×24 slab is a full truckload — a standard mixer truck carries about 10 cubic yards, so the 6-inch pour needs a second small load or a second truck.
How much concrete for a 10×20 slab?
At 4 inches thick: 2.47 cubic yards — order 2.75 yards, or 112 bags of 80-lb mix. At 6 inches: 3.70 cubic yards — order 4.25 yards, or 167 bags. Ready-mix concrete is roughly $344–$495 at 4 inches, before delivery.
Is a 24×24 slab a bag job?
No. Even at 4 inches it takes 320 bags — 25,600 lb of dry mix — and at 6 inches it is 480 bags, over 19 tons. Order ready-mix: the 6-inch slab orders 11.75 yards, more than one standard 10-yard truckload, so discuss the split with the supplier before the pour.
Sources and Method
The constants and rules of thumb on this page come from the published references below. Where a figure is a range, the calculator uses the mid-range value and the text says so.
- NRMCA CIP 31 — Ordering Ready-Mixed Concrete (ready-mix ordering and waste guidance).
- QUIKRETE Concrete Mix No. 1101 data sheet — published yield per bag (0.30 / 0.45 / 0.60 cu ft for 40 / 60 / 80 lb bags).
- Standard concrete density of about 150 lb per cubic foot.
- QUIKRETE Concrete Mix No. 1101 data sheet (PDF) — yield per bag: 0.30 cu ft (40 lb), 0.375 cu ft (50 lb), 0.45 cu ft (60 lb), 0.60 cu ft (80 lb); mixing water about 6 pt per 80 lb bag. Checked November 2026.